If the pile is blocked during pile driving and the driving doesn't continue with success, use drilling to make the "blocked" pile empty. Then continue with pile driving.
Pile Driving for Wikinger OWF
Take a hydraulic hammer to put the piles into the ground of the sea. These piles are the fix points for jacket installation.
Pre Trenching IAC Wikinger OWF
pre trench with a plough the designed cable routes inside the windfarm